RAMP ROAD WORKS AT LAYDOWN AREA
KSA
Project Overview
Scope of Work
Civil works; Major work volume: 360 M2; Peak manpower: 12 man-days/day; Accumulated manpower: 260 man-days
Project IDPOOL-013
Owner / ClientSAUDI ARAMCO
Main ContractorSAMSUNG E&A ARABIA CO.LTD.
LocationKSA
CategoryCivil
Start Year2025
End Year2025
StatusCompleted
PO / Reference NumberSA139F
Add a featured image in the project editor.
BOILER VESSEL MECHANICAL WORK
KSA
Project Overview
Scope of Work
Civil works; Major work volume: 1 Lot; Peak manpower: 26 man-days/day; Accumulated manpower: 75 man-days
Project IDPOOL-001
Owner / ClientSAUDI ARAMCO
Main ContractorDOOSAN ENERBILITY
LocationKSA
CategoryCivil
Start Year2024
End Year2025
StatusCompleted
PO / Reference NumberJCP-A-499