Civil

HORIZONTAL DIRECTIONAL DRILLING(HDD) FOR INSTALLATION OF HDEP PIPES FOR 115KV CABLE ROUTE

KSA

Add a featured image from the project editor.

Project Overview

Scope of Work

Civil works; Major work volume: 1440 MTR; Peak manpower: 40 man-days/day; Accumulated manpower: 6240 man-days

Project IDPOOL-020
Owner / ClientSAUDI ARAMCO
Main ContractorSAMSUNG E&A ARABIA CO.LTD.
LocationKSA
CategoryCivil
Start Year2025
End Year2025
StatusCompleted
PO / Reference NumberSA139F